PROJECT 110 UTILITIES

AL-KAYAN, Egypt
Construction supervision

Client:

Engineering Authority - Department of Military Works
Budget:
---
Contracting date:
June 2018
Status:
Delivered

OUR ROLE:

Owner’s Consultant

Project description:

The project consists of:
• Main drainage network with total length of about 87 km.
• Main irrigation network with total length of about 85 km.
• Sub-networks (drainage, water, irrigation and roads).
• (13) pumping stations.
• (18) storage ground water, irrigation and fire tanks.
• One main irrigation lift.
• Force main lines from the project to the treatment plant.
• Irrigation transmission line diameter 1000 mm from the treatment plant to the main irrigation crane project.

Hydro scope:

All site supervision duties and project management and/or coordination including reviewing all workshop drawings and assuring that all quality standards are implemented.