OBOUR STEEL FACTORY

Obour city, Egypt
Shop drawing

Client:

Concord for Engineering & Contracting
Budget:
---
Contracting date:
January 2021
Status:
In Progress

OUR ROLE:

Contractor’s Consultant

Project description:

Steel factory at the industrial area of Obour City, the steel fabrication process includes (Forming mill - ENF beveling - Hydro test - coating), the factory consists of:
• Administrative building 594.6 m2.
• Security building 16.275 m2.
• Electric transformer (2), (1) rooms 122 m2.
• Factory hangar 37183 m2.
• Staff break building.

• Pump house.
• Electric Generator.
• Electric panels Building 187 m2.
• Loading Area.

Hydro scope:

Prepare Design’s for Electrical components:

• MV network.
• LV Network.
• 2 Dry transformers.
• Medium voltage switchgear.

• Low voltage switchgear 4000A 0.4V.
• Emergency lighting and standby generator.
• 3 Separate earthing systems (Transformers - Generator - Control Panels).

 

Light current network:
• Fire Alarm.
• Telephone System.
• CCTV Network.