Skip to content

Irrigation Water Transfer (from Eastern Source to Mostakbal Misr 2 project) – 400,000 Feddans

Giza, Egypt
Design  Construction supervision

Client:

Egyptian Air Force
Budget:
---
Contracting date:
Status:
In Progress

OUR ROLE:

Owner Design & Supervision Consultant

Project description:

Mostakbal Masr is a national project that aims to deliver 10 million m3 per day of irrigation water, (5 million m3 per day for 400,000 feddans and 5 million m3 per day for 300,000 feddans) from the Mostakbal Misr Project (1) to the west of the ring road and the west of the Sheikh Zayed City to irrigate 229028 feddans.

The project consists of the following:

  • 4 Pipelines with a total length of 2,320,636 m. (Main pipelines: 477,782 m , sub pipelines: 1,842,854 m).
  • Open channel with the length of 25,000 m.
  • Estimated electrical capacity is 17.9 Megawatt.
  • (2) Main pumping stations.
  • (2) Regulators.
  • (2) Bridges.

Hydro scope:

  • Preparing the design drawings and supervision on all different works for coverage area 400,000 feddans including: (Hydraulic – Architectural – Structural – Mechanical – Electrical – Roads).
  • Supervision on all different works for coverage area 300,000 feddans to ensure execution quality and the construction is going according to designs and standards.

Subscribe to receive the latest newsletter

Be the first to know our latest trends and get exclusive offers