The New Urban Communities Authority (NUCA)
Client’s Consultant
The New Urban Communities Authority (NUCA)
1.1 billion
230 Feddans
New Administrative Capital - EGYPT
December 2022
Supervising the installation of the following systems:
Sewage Line: Concrete pipes, 1200 mm diameter, with a total length of 2,566 meters.
Sewage Network: UPVC pipes, spanning 7,770 meters in total.
Stormwater Network: HDPE/UPVC pipes, covering 9,424 meters, PN 6.
Water Network: HDPE pipes, with a total length of 12,563 meters, PN 16.
Irrigation Network: HDPE pipes, extending 12,312 meters, PN 10.
Fire Network: HDPE pipes ranging from 160mm to 500mm, with a total length of 11,415 meters.
Medium Voltage Distributors: Five units.
Medium Voltage Network: M.V. Cable (3*400) mm2, L= 96 km & (3*240) mm2, 50 km
Low voltage Network and Grounding Systems, LV. Cables totaling 89 km
Electrical Systems for street lighting, lighting cables, covering 142 km
Construction Supervision