New Urban Communities Authority
Client’s Consultant
New Urban Communities Authority
EGP 2.8 billion
New Administrative Capital – Cairo, Egypt
February 2023
The construction supervision of involved disciplines for the 1500 mm diameter irrigation water transmission pipelines from the wastewater treatment plant to the irrigation storage tanks and pump station in the R8 area:
Pump Room 1:Phase 1(2 working +1 standby) & Phase 2(3 working + 2 standby) : Q / pump = 116,760 m³/day, head of 158 m Pump Room 2:Phase 1(One working +One standby) & Phase 2
(2 working + 2 standby): Q / Pump = 45,000 m³/day, head of 90 m
Station components:
| ·Fence, Main Gate & Guard room | ·Administrative building & Mosque | ·Service Transformer Building |
| ·Guard Towers | ·Water hammer room | ·Electrical Control Panel Building |
| ·Suction Pit and Pump Room | ·Generator House & Fuel tank | ·Workshop and Warehouse building |
| ·Underground Storage Tanks | ·Inlet Valve Chambers | ·Emergency Exit Gate |
| ·Power Transformer Building | ·Distribution Valve Chambers on the 1800 mm Pipeline | ·Flow measurement chamber at the 100 mm outlet & the 1800 mm Outlet |
Construction Supervision