6th of October City Authority
Client’s Consultant
6th of October City Authority
EGP 980 million
3,482 feddans
6th of October City, Egypt
May 2020
Design and Supervision of:
Sewage Network (Drainage and Storm): UPVC pipes (160, 200,250, and 315 mm), L = 370 km, concrete pipes (800 to 1600 mm), L= 9180 linear meters and vitrified clay pipes (300 to 600 mm) with a total length of 23444 linear meters, including 145 rectangular sewage manholes, 6126 circular sewage manholes, and 2050 stormwater manholes.
Irrigation Network: HDPE irrigation pipes (100 mm to 250 mm) with a total length of 112 km .
Water Network: UPVC pipes (110 mm to 600 mm) with a total length of 350 km, along with 35 valve chambers of various prototypes.
Firefighting: 625 ductile iron fire hose connections (2.5 inches, with 2 openings).
Roads: L= 2076 meters.
Conceptual design and detailed design
Tender documents
Construction Supervision