El Dabaa Nuclear Power Plant

Client

The Nuclear Power Plants Authority

Our Role

Contractor’s Consultant

Contractor

Titan 2

Budget

US$ 30 billion

Pipeline Diameter

1,000 and 3,000 mm

Location

El Dabaa - Egypt

Project Date

March 2025

Project Description

Preparation of detailed shop drawings for the GRP cooling water pipelines serving Units 3 and 4 of Egypt’s El Dabaa Nuclear Power Plant.

Scope of Work

  • Preparation of detailed documentation for manufacturing and installing the cooling water system GRP pipes.
  •  GRP pipe diameters of 1,000 and 3,000 mm for Units 3 and 4.
  •  General assembly drawings.
  •  Installation layouts.
  •  Isometric drawings showing pipe components, dimensions and support details.
  •  Coordination of drawings and calculations with the Amantit supplier data sheets.
  •  Compliance with AWWA M45 and AWWA C950 standards.
  •  Coordination with civil engineering designs.
  • Obtaining formal approval from the main contractor, Titan 2 / Rosatom.

Hydro Services

  •  Shop Drawings

Project Gallery

Project Video