Skip to content
Home
About
Engineering Services
Engineering Divisions
Selected Experience
Join Us
News
Contact Us
X
Request Consultation
Home
About
Engineering Services
Engineering Divisions
Selected Experience
Join Us
News
Contact Us
X
East Port Said Sewage PS
East Port Said, Egypt
Pump Stations
April 2020
Client
The Suez Canal Economic Zone
Budget
EGP 350 million
Capacity
PS1 500 L/s; PS2 200 L/s
Network Length
Overview
Scope of Work
Technical Highlights
Gallery
Project Overview
Detailed design, shop drawings and as-built drawings for two pump stations and site components.
Scope of Work
Detailed design, shop drawings and as-built drawings for two pump stations and site components.
Technical Highlights
PS1 500 L/s; PS2 200 L/s
Capacity
Network Length
EGP 350 million
Budget
April 2020
Date
Project Gallery
Related Projects
NAC Tertiary WWTP
Egypt
250,000 m³/day
NAC Utility Supervision
Egypt
Storm/sewage/water/irrigation utility package
Matrouh Villages Sewage
Egypt
Village wastewater collection and transfer systems
↑