East Port Said Sewage PS
East Port Said, Egypt
Pump Stations
April 2020
Client
The Suez Canal Economic Zone
Budget
EGP 350 million
Capacity
PS1 500 L/s; PS2 200 L/s
Network Length
Overview
Scope of Work
Technical Highlights
Gallery
Project Overview
Detailed design, shop drawings and as-built drawings for two pump stations and site components.
Scope of Work
Detailed design, shop drawings and as-built drawings for two pump stations and site components.
Technical Highlights
PS1 500 L/s; PS2 200 L/s
Capacity
Network Length
EGP 350 million
Budget
April 2020
Date