SCZone Water PS

Suez Canal Economic Zone / East Port Said, Egypt

March 2021 and January 2022

Client

Water Department - Engineering Authority

Budget

EGP 2.2 billion

Capacity

150,000 m³/day pump station; 6 tanks

Network Length

Project Overview

Concept, detailed design, tender documents and construction supervision for pipeline, pump station, tanks, buildings and site works.

Scope of Work

Concept, detailed design, tender documents and construction supervision for pipeline, pump station, tanks, buildings and site works.

Technical Highlights

150,000 m³/day pump station; 6 tanks

Capacity

Network Length

EGP 2.2 billion

Budget

March 2021 and January 2022

Date

Project Gallery