Relocation of Borg El Arab Water Station Intake from Mariout Canal (Km 40) to Nubaria Canal (Km 83.7)

Client

Construction Authority for Potable Water and Wastewater (CAPW)

Our Role

Contractor’s Consultant

Contractor

Concord for Engineering and Contracting

Budget

EGP 640 million

Capacity

660,000 m³/day

Location

Alexandria - Egypt

Project Date

February 2016

Project Description

The project aims to operate the Mariout 1 station by utilizing water from the Al-Omum Drain at kilometer 85 of the Nubaria Canal, providing 2 million m3/day. It will blend Desert Reclamation Drain water with Mariout Canal water for agricultural use, thus conserving Nubaria Canal water. The project will also improve the quality of drinking water to meet the Egyptian Ministry of Health standards and international guidelines. Additionally, it will reduce operational costs for lifting turbid water to the 40-kilometer treatment plant by connecting directly to the clarifiers and lower maintenance costs for lifting pumps. Reusing 65,000 cubic meters of water in the second phase is also part of the plan.

Scope of Work

Preparing shop drawings and as-built of :

  • Raw Water Intake: Nubaria Canal at km 83.7 with a Capacity: 660,000 m³/day
  • Raw Water Pumping Station:11 working pumps (2,500 m³/h each) + 6 standby pumps Head: 28 m, Electrical: 225 KW/pump, 2 sumps (31×7×2.77 m)
  • Transmission Pipelines:3 pre-stressed concrete lines, 1600 mm dia., 13.4 km (total 40 km)
  • Pump Station Buildings: Workshops, stores, fuel tank, transformer, generator, administration, security, low-voltage room, general site works
  • Hydraulic Lines:2 steel pipelines (800 mm) serve 17 pipelines (600 mm)
  • Valve Chambers: Main valve, water hammer system, 4 flushing, 7 air, 5 flushing/maneuvering, 2 flow meter chambers
  • Crossings:Marioublis Canal, Tahrir Drain, Railway, Nubaria Drain
  • Distribution Chamber: Size: 12.5 × 8.5 × 14 m Entry: Three 1600 mm pipelines Exit: One 1200 mm, three 1500 mm, one surplus 1000 mm pipeline, Sludge Chamber : Collects raw water for sludge separation and reuse
  • Connections to Distribution Networks: Degremont Outlet: 1200 mm (400 m), Hors Outlet: 1500 mm (50 m) and Future steel pipeline: 1500 mm diameter

Hydro Services

Shop Drawings

As-built Drawings